Medical Office Drywall Takeoff Case Study: 4,350 SF Clinic Tenant Improvement in Idaho
Drywall, finishes, roll-on texture, FRP and cement board for an outpatient clinic in an existing building, measured on five sheets in Bluebeam.
Case Study • Healthcare TI • Idaho
The short answer
We took off the drywall scope for a 4,350 SF medical clinic tenant improvement in an existing one-story building in Idaho: 29 rooms, new wood-framed partitions by others, a tiled restroom, an FRP janitor room and texture to match existing walls. The takeoff has 89 line items and a 23-line material list: 30 sheets of 5/8" gypsum board, 9 sheets of moisture-resistant board, 9 sheets of 1/2" cement board, 8 FRP panels, 24 pails of texture compound for 10,367 SF of roll-on texture, and 14 patch and repair locations. Quantities only.

Project Snapshot
| Item | Detail |
|---|---|
| Project | Medical clinic tenant improvement (Group B) |
| Building | Existing building, 1 story, interior TI |
| Size | 4,350 SF gross, 29 rooms |
| Location | Idaho |
| Drawings | Issue for AHJ Review dated 10/30/26, plus Addendum 1 (electrical only; confirms the reception hard-lid ceiling) |
| Sheets measured | Demolition plan, dimension plan, reflected ceiling plan, enlarged plans and elevations, finish plan |
| Scope ordered | Drywall boards and ceilings, finishing and roll-on texture, trims, sealants, FRP and cement board |
| By others | Wood studs, blocking, backing and ceiling framing; insulation; acoustical ceiling tile and grid |
| Waste | 5% on board, cement board, trims and sealants; 10% on FRP |
| Deliverables | Excel workbook (Takeoff, Notes, Material List) + 5-page Bluebeam markup PDF |
Project Overview
This tenant improvement turns part of an existing single-story building into an outpatient clinic: exam rooms, a procedure room, provider and billing offices, a lab, a pharmacy with a pass-through window, a reception and nurse station, a break room, a janitor and storage room and a restroom. Part of the suite is marked not in scope. The new partitions are wood framed by others, so the drywall contractor's work is board, finish, texture, FRP, cement board, trims and sealants.
That makes a clinic TI a different kind of drywall takeoff from new construction. A large share of the drywall labor is on walls that already exist: the finish plan asks for roll-on texture to match existing, the demolition plan creates tie-ins and patches, and the restroom adds cement board to existing walls as well as new ones. A drywall takeoff that counts only new wall lines would miss most of the finishing.
The drywall heights are set by the drawings, not by the building: new partitions take 5/8" board on both faces to 6" above the adjacent ceiling (the wall legend, a ceiling note and the partition detail all agree), the janitor and restroom ceiling is moisture-resistant board at 8'-0", and the reception and pharmacy niche have gypsum soffits at 7'-7". Each of those is its own line in the takeoff.
Why Medical Office TI Drywall Takeoffs Are Different
1. Most of the drywall finishing is on existing walls
The finish plan required roll-on texture to match existing. We carried it as its own block so it can be removed in one step if the painter carries texture: one line for new board (1,334 SF) and 26 room-by-room lines for existing wall faces (9,032.5 SF). Existing faces were traced on the finish plan and multiplied by each room's ceiling height, with no deduction for doors or existing windows, and without storefront glazing, open sides, casework-covered walls or new walls.
2. Wet and clean rooms change the board, the finish and the trim
The restroom gets 1/2" cement board to 5'-0" on every tiled face, on new and existing walls, with moisture-resistant board above the tile. The janitor and storage room gets 0.090" FRP over moisture-resistant board, taped only to Level 2 because the FRP covers it, with inside and outside corners, division bars and J-cap. The finish schedule gave the FRP no height, so the takeoff carries it full height to the 8'-0" ceiling on all four walls and the notes say so, with the wainscot alternative stated for the reviewer.
3. Scope lines with other trades are tight
On a clinic TI the drywall scope touches framing, ceilings, tile, paint and electrical. This takeoff writes the boundary down: wood studs, blocking, backing and ceiling framing by others; insulation by others; acoustical ceiling tile and grid by others; tile, paint and primer, and access panels not included; the existing tenant demising walls not field-verified or upgraded; and acoustical putty at outlet boxes left to the electrician. Bidding those lines in or out is a pricing decision, so the takeoff makes each one visible.

How We Measured the Drywall Scope
Five sheets were marked in Bluebeam Revu at 3/16" and 3/8" = 1'-0", with the scale checked against printed dimensions on each sheet. Every drywall quantity in the workbook ties back to one of those markups.
- Demolition plan: removed walls, new openings in existing walls and tile removal, counted as 14 patch and repair locations (both faces where both faces are affected).
- Dimension plan: every new partition traced by wall type and height, plus the storefront header at the ceiling, the infills over new doors and the board returns at the new pharmacy pass-through window.
- Reflected ceiling plan: the gypsum ceiling over the janitor room and restroom, the soffits at reception and the pharmacy niche, and the soffit faces from 7'-7" to 9'-0". Acoustical tile and grid are left to others.
- Enlarged plans and elevations: the restroom's cement board and MR board heights, the FRP room and the corner bead at the divider end above the tile.
- Finish plan: existing wall faces marked for texture, room by room, and the FRP and finish locations.
- Material list: drywall board, cement board, compound, texture compound, screws, trims, FRP and sealants converted from the line items and rounded up once per item.



One Wall, Line by Line: the Janitor Room
The janitor and storage room shows how one short wall turns into six kinds of material in a clinic drywall takeoff. These lines come straight from the delivered workbook:
| Takeoff line | Quantity | How it is figured |
|---|---|---|
| W6-P wall, janitor room, H=9'-0" | 15.48 LF | 14.74 LF measured + 5% waste |
| 5/8" gypsum board, outer face | 139.3 SF | 15.477 LF × 9'-0" |
| 5/8" moisture-resistant board, janitor face (FRP substrate) | 131.6 SF | 15.477 LF × 8'-6" |
| 0.090" FRP, all four janitor room walls | 227.0 SF | 25.79 LF + 10% = 28.37 LF × 8'-0" → 8 panels of 4'x8' |
| FRP inside corners / outside corner / division bars | 24 / 8 / 32 LF | 3, 1 and 4 pieces at 8'-0" |
| FRP J-cap (top, bottom and open edge) | 62.6 LF | 59.58 LF + 5% → 8 pieces |
| Level 2 finish behind the FRP | 156 SF | board covered by FRP is not taken to Level 4 |
Miss any one of those lines and the bid is short: the MR board, the FRP trims and the lower finish level are exactly the items a quick square-foot drywall estimate leaves out.

The Numbers
New drywall wall lines, measured by length (both faces board unless noted):
| Wall line | Height | Length |
|---|---|---|
| W4-P partitions, 5/8" GB both sides to 6" above ceiling | 9'-0" | 31.56 LF |
| W6-P partitions, 5/8" GB both sides to 6" above ceiling | 9'-0" | 10.94 LF |
| W4-P reception north and pharmacy window wings (soffit side to 7'-7") | 9'-0" | 18.83 LF |
| W6-P janitor room walls (MR on the janitor side, FRP substrate) | 9'-0" | 14.74 LF |
| W6-P janitor / restroom divider | 8'-6" | 4.79 LF |
| W6-P / W4-P restroom walls (restroom side tiled) | 9'-0" | 9.73 LF |
| Existing restroom walls (cement board and MR on existing faces) | 8'-6" | 10.37 LF |
| Storefront header at the ceiling, both sides | 8'-0" to 9'-0" | 14.28 LF |
| Soffit face, reception and pharmacy niche | 7'-7" to 9'-0" | 20.14 LF |
| Pharmacy pass-through window returns (new opening) | head and jambs | 10 LF |
Finishing and texture, measured by area:
| Drywall finish line | Quantity |
|---|---|
| Level 4 finish, new exposed wall board | 1,334 SF |
| Level 4 finish, gypsum ceiling and soffits | 199 SF |
| Level 2 finish, board behind FRP | 156 SF |
| Level 1 finish, board above the ceiling | 129 SF |
| Cement board joints (mesh tape and setting compound) | 124 SF |
| Roll-on texture, new board | 1,334 SF |
| Roll-on texture, existing walls (26 room lines from 1,032.5 LF of wall face) | 9,032.5 SF |
| Patch and repair, existing gypsum board | 14 locations |
And the drywall material list, the order the contractor can send to the supplier with a quote request:
| Material | Order quantity |
|---|---|
| 54"x12' x 5/8" gypsum board (walls, hung horizontal) | 26 sheets (1,404 SF) |
| 4'x12' x 5/8" gypsum board (soffits, soffit faces, headers, door infill) | 4 sheets (192 SF) |
| 4'x12' x 5/8" moisture-resistant board (janitor room, restroom walls and ceiling) | 9 sheets (432 SF) |
| 3'x5' x 1/2" Durock cement board | 9 sheets (135 SF) |
| Tape / all-purpose joint compound / setting compound / mesh tape | 3 rolls / 3 pails / 3 bags / 1 roll |
| Roll-on texture compound, 4.5 gal (new board / existing walls) | 3 / 21 pails |
| 1-1/4" Type W screws / cement board screws | 11 lb / 1 lb |
| 1-1/4" metal corner bead / 5/8" J-bead | 16 pcs (160 LF) / 6 pcs (60 LF) |
| 4'x8' x 0.090" FRP, Class A | 8 panels (256 SF) |
| FRP adhesive / inside corner / outside corner / division bar / J-cap | 6 gal / 3 / 1 / 4 / 8 |
| 3/8" backer rod / clear silicone (storefront, pharmacy window) / silicone (FRP, mop sink) | 93 LF / 8 tubes / 3 tubes |
Common Clinic TI Drywall Takeoff Mistakes This Avoids
- Pricing texture from new walls only. Here the existing walls carried 9,032.5 SF of texture against 1,334 SF on new drywall board. A takeoff that stops at new work misses most of the finishing.
- Treating every wall as Level 4. Board behind FRP and above the ceiling does not need Level 4; carrying it anyway overprices the drywall finishing.
- Forgetting cement board on existing walls. The restroom's existing walls get Durock and MR board too, on 10.37 LF of existing wall.
- Skipping patch and repair. Demolition creates tie-ins and openings; fourteen locations is a real line of labor on a small TI.
- Running partitions to the deck. The drawings take board to 6" above the ceiling. Carrying full-height walls adds drywall nobody asked for.
What the Contractor Received
A three-tab Excel drywall takeoff workbook and the five-page markup PDF:
- Takeoff: 89 line items grouped as hanging (walls, ceilings, soffits, headers, infill, trims), finishes and roll-on texture, FRP wall panels and sealants. Each line has its drawing sheet, detail reference, quantity, waste and unit, with open columns for material cost, labor wage and production rate.
- Notes, Assumptions & Exclusions: the basis (drawings, scales, waste), the scope rules for partitions, restroom, FRP and finish levels, the texture and ceiling assumptions, and every exclusion.
- Material List: 23 order lines, rounded once per item.


The complete workbook is published as a PDF with pricing removed: open the medical clinic TI sample takeoff.
Drywall Takeoffs for Idaho Projects
Idaho adopts the International Building Code statewide with state amendments; the Idaho Division of Occupational and Professional Licenses lists the 2018 IBC in its 2025 adopted-codes summary. For an outpatient clinic like this one (Group B), the drawings put most of the drywall requirements in the finish schedule and the wet rooms: moisture-resistant board, cement board behind tile and washable FRP in the janitor room. The one rated item on this set, taking the existing tenant demising walls to the deck at one hour, was left out of the takeoff for field verification and stated as an exclusion.
A tenant improvement in an existing building puts more of the drywall work on walls that are already there: texture to match existing, patches from the demolition plan, new board on existing restroom walls. Those are the lines that are easiest to leave out of a bid, which is why this takeoff lists them room by room. We do not have a separate Idaho page; the service areas page explains how remote takeoffs work for any state.
Outcome
The drywall contractor received a takeoff that separates new work from existing-wall work, so the bid can be priced and qualified in the same structure:
- Texture as a removable block. If the painter carries texture, one block and two material lines come out; nothing else changes.
- Wet rooms counted layer by layer. Cement board, MR board, FRP, Level 2 behind FRP and the FRP trims each have their own line.
- Assumptions in writing. FRP height, existing-wall texture rules, the reception hard-lid ceiling confirmed by the addendum and the base-bid rooms left as they are, all stated in the Notes tab.
Who This Is For
- Drywall contractors bidding medical office, dental, urgent care and clinic tenant improvements.
- General contractors carrying a TI who need the drywall, FRP and texture quantities checked before buyout.
- Interior contractors who self-perform board and finish but sub the framing and ceilings.
For larger healthcare projects, our drywall takeoff services cover rated corridors, shaft walls and ceiling assemblies the same way: see drywall estimating services, the metal stud framing takeoff page and the acoustical ceiling takeoff add-on. The finish levels guide explains the Level 1, 2 and 4 split used here.
Medical Office Drywall Takeoff FAQs
What is included in a medical office drywall takeoff?
Every board, finish and accessory the drywall contractor installs: gypsum board on new partitions, headers, soffits and infills, moisture-resistant board and cement board in wet rooms, FRP where the finish plan calls for it, tape and compound by finish level, corner bead and trims, texture, patch and repair on existing walls, and sealants. On this clinic that came to 89 line items and a 23-line material list.
How much does a tenant improvement drywall takeoff cost?
Tenant improvement and commercial work up to about 12,000 SF is starting from $300 per project; single-family and remodel work is starting from $150 per project. You get a fixed price within 2-4 business hours of sending the plans, and rush delivery is +30%.
How long does a TI drywall takeoff take?
Most tenant improvement takeoffs are delivered in 24-48 hours. Full commercial sets take 3-5 business days. Revisions within 48 hours are free.
How do you measure roll-on texture on existing walls?
We trace the existing gypsum wall faces the finish plan marks for texture, multiply by the ceiling height of each room (9'-0" in the exam and office rooms, 8'-6" elsewhere on this project) and list the result room by room. Here 1,032.5 LF of existing wall faces gave 9,032.5 SF across 26 room lines, plus 1,334 SF on the new board.
How do you take off FRP wall panels?
FRP is measured by the wall length and height of each room that gets it, converted to 4'x8' panels with 10% waste, and paired with adhesive, inside and outside corners, division bars at panel joints and J-cap at the top, bottom and open edges. The board behind FRP is taped to Level 2, not Level 4.
Where does cement board go in a clinic restroom?
Wherever tile goes. On this project 1/2" cement board runs to 5'-0" on every tiled face of the restroom, on new and existing walls, with moisture-resistant gypsum board above the tile. Cement board joints get alkali-resistant mesh tape and setting compound, which are separate lines in the takeoff.
What finish level is used behind FRP panels?
Level 2: joint tape embedded in compound plus one coat over joints and angles. FRP covers the board, so Level 4 would be wasted labor. The takeoff carries Level 2 behind FRP, Level 4 on exposed board and Level 1 above the ceiling.
Do you count patch and repair on existing walls?
Yes, as a count of locations with the reason for each: removed-wall tie-ins, new openings in existing walls and wall patches where tile is removed. This clinic had 14 patch and repair locations, taken from the demolition plan.
Why do the new partitions stop 6 inches above the ceiling?
Because the drawings say so: the wall legend and ceiling notes take board to 6" above the adjacent ceiling, not to the deck. That one note sets the height of every new wall line, so it is written into the takeoff notes.
Is wood or metal stud framing included?
Not on this project: the new partitions were wood framed by others. When framing is in your scope, we take off studs, track, headers and backing by size and gauge as a metal stud framing takeoff.
Is the acoustical ceiling included?
No. Acoustical ceiling tile and grid were excluded here. ACT is available as an add-on to any drywall takeoff, counted by room with tile, main tees, cross tees, wall angle and hanger wire.
What drawings do you need for a medical office TI takeoff?
For a clinic drywall takeoff we need the demolition plan, new floor or dimension plan with wall types, reflected ceiling plan, enlarged plans and interior elevations of wet rooms, the finish plan and finish schedule, and any addenda. PDF is fine.
Do you do drywall takeoffs in Idaho?
Yes. Our drywall takeoff services work from the drawings, so Idaho projects get the same turnaround as any other state.
Is the takeoff delivered as an Excel spreadsheet?
Yes: every drywall takeoff comes as an Excel workbook with the takeoff, the notes and the material list, and a Bluebeam markup PDF of the marked sheets. The cost columns stay open for your own prices.
Related Services and Case Studies
Get a Takeoff Like This for Your Next Bid
Send the plan set and tell us the scope: drywall only, drywall with metal studs, or the full package with insulation or ACT. A project manager emails a fixed price within 2–4 business hours. Most takeoffs are delivered in 24–48 hours; full commercial and multifamily sets take 3–5 business days. Single-family and remodel work is starting from $150 per project, commercial and tenant improvement work is starting from $300 per project, and revisions within 48 hours are free.